Build a station-by-station schedule

Give each pickup point an identifier and document its required duty and operating schedule. Separate stations that can run together from those that are interlocked. Include changes such as a second line coming on before the first line stops.

Station duties → Concurrent cases → Header review
Original diagram: Station duties → Concurrent cases → Header review
02

Review capture in each agreed case

Ask the designer to review branch conditions and the fan and collector duty for the agreed combinations. Plan commissioning checks at the relevant hoods, including a lightly loaded case. Total airflow at the fan by itself cannot show how much reaches a particular branch.

One line → Overlap → Both lines
Original diagram: One line → Overlap → Both lines
03

FAQ: Can I size by adding all nameplate figures?

Use verified station requirements and known combinations. A summed figure does not establish branch balance or source capture.

Technical sources and editorial note

Technical concepts are independently summarized from the sources below; the quotation checklist is editorial guidance. The EPA manual is a historical engineering reference, not a current price guide or a statement of local compliance. Images are equipment references from the existing Kuohai website library, not evidence of a particular performance result. Sources reviewed on 2026-11-16.

Related equipment: Pulse jet baghouse dust collectors · Dust collector filter bags

Use this guide to prepare for an equipment discussion. Confirm selection and operating requirements against your actual process and site conditions.